목차
1. CM Case study
1.1 Project Outline (프로젝트 개요)
1.2 Organization Chart (조직도)
1.3 Planning Stage (기획단계)
1.4 Project promotion status (사업추진현황)
1.5 CM operation achievement accomplishment (업무수행실적)
1.6 Interview (인터뷰)
2. CM Process
2.1 CM Process (CM 프로세스)
2.2 Pre-Design phase (설계이전단계)
2.3 Design phase (설계단계)
2.4 Contract & Procurement phase (계약&구매단계)
2.5 Construction phase (시공단계)
2.6 Post-Construction phase (시공이후단계)
1.1 Project Outline (프로젝트 개요)
1.2 Organization Chart (조직도)
1.3 Planning Stage (기획단계)
1.4 Project promotion status (사업추진현황)
1.5 CM operation achievement accomplishment (업무수행실적)
1.6 Interview (인터뷰)
2. CM Process
2.1 CM Process (CM 프로세스)
2.2 Pre-Design phase (설계이전단계)
2.3 Design phase (설계단계)
2.4 Contract & Procurement phase (계약&구매단계)
2.5 Construction phase (시공단계)
2.6 Post-Construction phase (시공이후단계)
본문내용
1.1 Project Outline
★ Project : Susung Culture & Art Hall
★ Site : Daegu megalopolis Susunggu Jisandong
★ Construction Period : 2004. 05 ~ 2006. 05
★ Plottage : 18,305 ㎡
★ Company : Kunwon Engineering CM department
★ Project : Susung Culture & Art Hall
★ Site : Daegu megalopolis Susunggu Jisandong
★ Construction Period : 2004. 05 ~ 2006. 05
★ Plottage : 18,305 ㎡
★ Company : Kunwon Engineering CM department